India's coast is crowded with ports, tourism, fishing villages, industry and cities, and fragile with mangroves, coral reefs, sand dunes and turtle nesting beaches. Projects on the coast may need an environmental clearance under the EIA Notification, 2006 and a CRZ clearance under the Coastal Regulation Zone Notification, 2019. The first asks whether a listed project's overall impacts are acceptable; the second asks whether the activity is permissible at all in that particular zone of the coast. Where both are required, the Ministry issues a combined EC and CRZ clearance.
1. Environmental Clearance
Environmental clearance is required for projects listed in the Schedule to the EIA Notification, 2006, granted by the MoEFCC (Category A) or SEIAA (Category B) after screening, scoping, public consultation and appraisal, with conditions for environmental management and monitoring. It applies to listed projects wherever they are located, and it is impact-based: most projects can in principle be cleared with adequate mitigation.
2. CRZ Clearance
The Coastal Regulation Zone Notification, 2019 (notified on 18 January 2019 under the EPA, replacing the 1991 and 2011 Notifications) declares the coastal stretches, and the water area up to twelve nautical miles, as the Coastal Regulation Zone, and prohibits or regulates activities in it. The CRZ is divided into:
- CRZ-I: ecologically sensitive areas (CRZ-IA: mangroves, coral reefs, sand dunes, turtle nesting grounds, salt marshes and similar) and the intertidal zone (CRZ-IB);
- CRZ-II: developed areas within municipal limits;
- CRZ-III: relatively undisturbed rural areas, with a no development zone of 50 metres (in densely populated CRZ-IIIA areas) or 200 metres (CRZ-IIIB) from the high tide line; and
- CRZ-IV: the water area from the low tide line to twelve nautical miles, and tidal water bodies.
CRZ clearance is required for permissible activities in the CRZ. Projects in CRZ-I and CRZ-IV are considered by the MoEFCC, and those in CRZ-II and CRZ-III by the State Government or Union territory, in each case on the recommendation of the Coastal Zone Management Authority (CZMA). Projects that also attract the EIA Notification are appraised by the EIA authority with the CZMA's recommendation, resulting in an integrated clearance. Clearance must be consistent with the approved Coastal Zone Management Plan. Certain activities are prohibited outright (new industries, reclamation except for permitted purposes, discharge of untreated waste, destruction of mangroves and coral, and mining of sand from the CRZ except as permitted).
3. Key Differences
Basis | Environmental clearance | CRZ clearance |
|---|---|---|
Legal source | EIA Notification, 2006 under the EPA | CRZ Notification, 2019 (and Island Protection Zone Notification) under the EPA |
Trigger | Project listed in the EIA Schedule, anywhere | Any permissible activity within the Coastal Regulation Zone |
Approach | Impact-based: assess and mitigate | Zone-based: activity permitted, regulated or prohibited by zone |
Authority | MoEFCC (A) or SEIAA (B) | MoEFCC (CRZ-I, IV) or State/UT (CRZ-II, III) on CZMA recommendation |
Advisory body | EAC or SEAC | State or UT Coastal Zone Management Authority |
Basis of decision | EIA report, public hearing, appraisal | CRZ category, CZMP, permissibility list, CZMA recommendation |
Public participation | Public hearing (A and B1) | Through EIA where applicable; CZMP preparation involves consultation |
Prohibitions | None absolute | Absolute prohibitions (new industry, reclamation, mangrove destruction, etc.) |
Leading cases | Lafarge, Alembic | Maradu (2019), Kapico (2020), Bombay Environmental Action Group (2018) |
✦ Mnemonic: 'EC asks How much harm; CRZ asks Where on the coast' EC weighs how much harm a project will do and how to reduce it. CRZ first asks where on the coast the project is: in some zones the answer is simply no. Coaching analogy: EC is a medical fitness test; CRZ is a zoning map of a hospital, where some wards (CRZ-I) are sterile and no visitors are allowed, however fit they are. |
4. Case Law
- Kerala State Coastal Zone Management Authority v. State of Kerala (Maradu flats), (2019) 7 SCC 248: the Supreme Court ordered demolition of four high-rise apartment complexes built in violation of the CRZ Notification in an ecologically fragile area near Kochi, and they were demolished in January 2020, with compensation to flat owners;
- Kapico Kerala Resorts Pvt. Ltd. v. State of Kerala, (2020) 3 SCC 18: the Court upheld demolition of a luxury resort built on an island in Vembanad lake in violation of CRZ, holding that permissions granted by local bodies could not override the CRZ Notification;
- Bombay Environmental Action Group v. State of Maharashtra (Bombay High Court, 2018): a total freeze on destruction of mangroves (CRZ-IA) and a fifty-metre buffer; and
- Indian Council for Enviro-Legal Action v. Union of India, (1996) 5 SCC 281: the Supreme Court insisted on enforcement of the CRZ Notification, 1991 and on preparation of Coastal Zone Management Plans by the States.
⚠ Examination point Stress the impact-based nature of EC versus the zone-based nature of CRZ regulation, name the four CRZ categories and the approving authorities, mention the CZMA, and cite Maradu and Kapico to show that CRZ violations can lead to demolition even of completed buildings. |
✦ How to write a 10-mark answer on EC versus CRZ clearance 1. EC: source and process. 2. CRZ Notification, 2019: zones, prohibitions, CZMA, CZMP, approving authorities. 3. Integrated EC and CRZ clearance. 4. Differences table. 5. Cases: Maradu, Kapico, Bombay Environmental Action Group, ICELA (1996). 6. Conclusion. |
5. Related Topics and Provisions
Topic or provision | Connection |
|---|---|
Coastal regulation and eco-sensitive areas (Topic 21) | CRZ Notification in detail |
Environmental Impact Assessment (Topic 20) | EC in detail |
Marine and coastal environment (Topic 42) | Mangroves, corals and coastal erosion |
EC vs forest clearance (Topic 64) | Another parallel clearance |