Chapter VI is the socialist spine the motor vehicle law kept: where the State Government considers that public interest requires State operated road transport, it may formulate a scheme taking over routes or areas for its undertaking, to the partial or complete exclusion of private operators. Once approved and published, the scheme is law on that corridor, and Adarsh Travels settled that private permits cannot touch even an overlapping portion of a notified route.

1. The scheme machinery: sections 97 to 102

  • The actor: a State transport undertaking, the State's road transport corporation or department service.
  • Proposal, section 99: where the State Government is of opinion that for providing an efficient, adequate, economical and properly coordinated road transport service it is necessary in the public interest that the undertaking operate a route or area, with complete or partial exclusion of other persons, a proposal is prepared and published.
  • Objections and approval, section 100: affected operators and associations file objections; the State Government hears them and may approve or modify the scheme, publishing the approved scheme, which then has the force of law.
  • Modification and cancellation, section 102 follow their own notice and hearing procedure; section 103 directs the transport authorities to issue permits to the undertaking in accordance with the scheme, and section 104 restricts grants to others contrary to it.
  • Overriding effect, section 98: the Chapter and its schemes prevail over Chapter V and any inconsistent law, the provision that gives the approved scheme its teeth.

From proposal to monopoly

Figure 1: From proposal to monopoly

What a scheme can be

Figure 2: What a scheme can be

2. The Adarsh Travels rule

📖 Adarsh Travels Bus Service v State of U.P., (1985) 4 SCC 557

Facts: Approved schemes reserved certain routes to the State undertaking to the complete exclusion of private operators. Private operators holding permits on longer or intersecting routes claimed the right to ply over the portions that overlapped the notified routes, without picking up or setting down passengers on the overlap.

Held: A Constitution Bench held they could not: where an approved scheme excludes private operators from a notified route, a private permit holder cannot ply over any part of it, even an overlapping stretch of a different route and even on a corridor restriction basis.

Ratio: The scheme's exclusion is territorial and complete; permitting overlap operation would erode the monopoly the scheme creates and invite the very competition the Chapter authorises the State to eliminate. The scheme, having the force of law, overrides permit rights under the general Chapter.

  • The sequel case law polices the consequences: deviations, corridor claims and curtailed permits are all read against the scheme's words, and a scheme's own savings, for existing operators, city services or specified classes, are construed as written.
  • Constitutional footing: State monopoly in road transport is protected by Article 19(6)(ii), so the exclusion of private trade under an approved scheme withstands the freedom of trade challenge.

Testing a private permit against a scheme

Figure 3: Testing a private permit against a scheme

3. The scheme in today's transport economy

  • Nationalised corridors persist in several States, intercity trunk routes above all, and permit litigation on them continues to apply the Chapter VI framework.
  • Policy has layered access: stage carriage liberalisation, tourist and contract carriage growth and the 2019 scheme provisions operate around the notified routes without displacing the exclusions.
  • For claims and enforcement, a private vehicle carrying passengers on a notified route operates without a valid permit for that use, with the penalty and insurance consequences that follow.

⚠ Key point

The sequence is proposal, publication, objection, hearing, approved scheme with the force of law; section 98 makes the Chapter override permit law, and Adarsh Travels (1985) 4 SCC 557 bars private operation over even an overlapping portion of a completely excluded route. State monopoly here rests on Article 19(6)(ii).

4. Quick Revision

✦ Chapter VI in five lines

Section 99: proposal in the public interest; efficient, adequate, economical, coordinated.

Section 100: objections heard; approved scheme published, force of law.

Sections 103 and 104: permits to the STU; contrary grants restricted.

Section 98: overriding effect over Chapter V.

Adarsh Travels (1985): no private plying on any part of a completely excluded route.

  1. Read the scheme's words before the permit's.
  2. Treat the approved scheme as subordinate legislation.
  3. Bar overlap operation on excluded routes.
  4. Apply the scheme's own savings strictly.
  5. Anchor the monopoly in Article 19(6)(ii).

5. Frequently Asked Questions

Can an existing permit holder claim compensation when a scheme takes his route?

The scheme framework works by curtailment, not expropriation with compensation. When a route is notified, existing permits are cancelled, curtailed or modified as the approved scheme provides, and the displaced operator's protections are procedural, the published proposal, the right to object and be heard, and judicial review of a scheme approved without that process or beyond the statutory conditions. A permit is a licence to use the road, not property in the route, so its curtailment under a lawful scheme has not been treated as acquisition demanding compensation; schemes themselves sometimes soften the blow by absorbing operators or saving limited services. The operator's real remedies are therefore at the scheme stage, in objections and challenge, not in a later claim for the route's value.

Do nationalised schemes still make sense in the app era?

The question divides policy, and the law holds both layers. The case for the scheme was universal service: a State undertaking cross-subsidises loss making rural routes from trunk corridors, which competition would cherry pick; the case against is the familiar monopoly critique, aging fleets and fiscal stress in the undertakings. The 1988 Act's liberalisation, the tourist and contract carriage boom and the 2019 scheme provisions for shared mobility have all grown around the notified corridors rather than through them, and States have periodically denotified routes where the undertaking cannot serve them. For an exam answer the legal position is the stable part: Chapter VI remains in force, approved schemes retain their overriding effect, and change comes route by route through section 102's modification machinery, not by judicial dilution.

What happens if a State undertaking fails to run the notified services?

The scheme does not lapse by neglect, but the law gives the gap three outlets. The State may modify or cancel the scheme under section 102's procedure, restoring the route to the ordinary permit system; the transport authorities may grant temporary permits to private operators where the undertaking's services are absent and public need is pressing, a bridge the case law allows strictly and briefly; and mandamus has issued against undertakings and governments where notified corridors were simply abandoned while private operators remained excluded, since the monopoly's justification is the service it promises. What courts refuse is the shortcut of ignoring the scheme: until modified, it binds, and unauthorised private operation remains plying without a permit however empty the route.

6. Related Topics and Provisions

  • Necessity of permits: section 66
  • Transport authorities and the grant of permits
  • Stage, contract and goods carriage permits
  • Tourist and national permits: section 88
  • Constitutional framework of motor vehicle law
  • Permit duration, transfer and cancellation