Right to Fair Compensation Act
Foundations and Constitutional Framework of the RFCTLARR Act, 2013: Complete Notes (Part A)
This consolidated note covers the whole foundation of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013: the history that produced it, the constitutional law it sits in, its preamble and salient features, the Section 2 gateway with its consent thresholds, and the Section 3 definitions that distribute everything the Act gives. It corresponds to Topics 1 to 15 of this series, which take each strand in finer detail.
1. From 1824 to 1894: The Colonial Law
Compulsory acquisition entered India with Bengal Regulation I of 1824, spread Presidency by Presidency (Act XXVII of 1839 for Calcutta, Act XX of 1852 for Madras), was consolidated for all India by Act VI of 1857 and refined by Act X of 1870, which introduced market value and the civil-court reference. The Land Acquisition Act, 1894 then fixed the procedure that governed for 119 years: preliminary notification (Section 4), objections to the Collector (Section 5A, added only in 1923), declaration (Section 6), award (Section 11), possession (Section 16), and an urgency clause (Section 17) that could bypass the only hearing the Act gave. Compensation was market value with 15% solatium, raised to 30% solatium with a 12% additional amount by the 1984 amendment.
2. Property and the Constitution
The Constitution of 1950 made property a fundamental right, Articles 19(1)(f) and 31, and three decades of Court-Parliament conflict followed: the First Amendment (1951) added Articles 31A and 31B with the Ninth Schedule; after Bela Banerjee (1954) read compensation as a just equivalent, the Fourth Amendment (1955) made adequacy non-justiciable; R.C. Cooper (1970) revived scrutiny of illusory compensation and the Twenty-fifth Amendment (1971) substituted "amount" and added Article 31C; Kesavananda Bharati (1973) gave the contest its lasting product, the basic structure doctrine. The Forty-fourth Amendment (1978) ended the era: Articles 19(1)(f) and 31 were deleted and property became Article 300A, a constitutional right outside Article 32. Legislative competence lies in Entry 42 of the Concurrent List, "acquisition and requisitioning of property" (so recast by the Seventh Amendment, 1956), which is why both Parliament and the States legislate and why Article 254(2) lets Presidentially assented State amendments prevail locally, the route States took after 2015. Article 31A still saves agrarian-reform acquisition (with a market-value proviso for cultivated ceiling-limit land), and Ninth Schedule entries added after 24 April 1973 are reviewable on basic structure grounds (I.R. Coelho, 2007).
Article 300A has since been given real content. K.T. Plantation (2011) implied public purpose and non-illusory compensation into "authority of law"; property was recognised as a human right the State cannot defeat by inaction or adverse possession (Vidya Devi, 2020; Sukh Dutt Ratra, 2022); and Kolkata Municipal Corporation v. Bimal Kumar Shah (2024) unpacked the Article into seven procedural sub-rights: notice, hearing, reasoned decision, public purpose, fair compensation, an efficient process, and conclusion in vesting. The 2013 Act is this jurisprudence in statutory form.
3. The Fall of the 1894 Act
- The defects: no consent and no real participation; an elastic public purpose that served private companies through Part VII; the urgency clause as routine; compensation pegged to understated circle rates and sale deeds; protection for recorded owners only; and no rehabilitation at all, nothing for the tenant, the labourer, the artisan or the displaced village.
- The flashpoints: Singur (2006), where acquisition for Tata Motors' plant was later quashed in Kedar Nath Yadav (2016); Nandigram (2007), where an SEZ proposal ended in firing and deaths; Bhatta Parsaul (2011) and the Greater Noida cases, where urgency acquisitions fell for colourable exercise (Radhy Shyam, Dev Sharan, 2011).
- The judicial verdict: in Ramji Veerji Patel (2011) the Supreme Court called the 1894 Act outdated and fit for replacement by comprehensive legislation, an unusual judicial call for repeal that the 2013 Act answered.
4. The Making of the 2013 Act
Date | Event |
|---|---|
2003, 2007 | National R&R policies: entitlements stated, not enforceable |
2007 to 2009 | Twin Bills (LA Amendment and R&R) pass the Lok Sabha, lapse with dissolution |
7 September 2011 | Integrated LARR Bill, 2011 introduced (Ministry of Rural Development, Jairam Ramesh), from the NAC draft |
17 May 2012 | Standing Committee on Rural Development reports |
29 August 2013 | Passed by the Lok Sabha |
4 September 2013 | Passed by the Rajya Sabha |
27 September 2013 | Presidential assent: Act 30 of 2013 |
1 January 2014 | The Act comes into force |
1 January 2015 | Section 113 order aligns Fourth Schedule enactments on compensation and R&R |
The 2014 Ordinance and the 2015 Amendment Bill, which would have exempted five project categories from consent and SIA, failed in Parliament, leaving the 2013 text standing at the Centre and pushing dilution to the States under Article 254(2) (Topics 94 to 96).
5. Preamble, Objects and Salient Features
The preamble promises a humane, participative, informed and transparent process, carried out in consultation with local self-government and Gram Sabhas, with the least disturbance to owners and affected families; just and fair compensation; rehabilitation and resettlement; and the ambition that affected persons become partners in development, better off after the acquisition than before it. The Act is beneficial legislation and is construed accordingly. Its salient features: consent of 80% and 70% of affected families for private and PPP acquisitions; Social Impact Assessment with public hearing and expert appraisal; the food-security bar on multi-crop land (Section 10); compensation of up to twice market value in urban and four times in rural areas through the multiplier and 100% solatium; a distinct R&R award for every affected family with Second and Third Schedule entitlements; SC/ST safeguards (Sections 41 and 42); urgency confined to defence and calamities (Section 40); Section 24 transition relief; return of land unutilised for five years (Section 101); the LARR Authority; offences and penalties; R&R duties on large private purchases (Section 46); and Fourth Schedule alignment (Section 105). The Act runs to 114 sections, thirteen chapters and four Schedules: compensation (First), R&R entitlements (Second), resettlement amenities (Third), exempted enactments (Fourth).
6. Eminent Domain Disciplined
The Act does not create the power it regulates. Eminent domain is the inherent sovereign power to take private property, resting on salus populi suprema lex and necessitas publica major est quam privata, and conditioned always on public purpose and compensation. Judicial review polices the edges: fraud on power, colourable exercise, procedural breach and arbitrariness (Sooraram Pratap Reddy, 2008), the grounds on which the Greater Noida and Singur acquisitions fell. The 2013 Act is best understood as a code of conditions on that power: the purpose enumerated and tested, the compensation formularised, the residue of fairness supplied by R&R, the food-security bar and the return of unused land.
7. The Section 2 Gateway and the Consent Referendum
Limb | Trigger | Consent | What applies |
|---|---|---|---|
Section 2(1) | Appropriate Government acquires for its own use, PSUs, public purpose | None | The full Act: SIA, compensation, R&R |
Section 2(2)(a) | Acquisition for PPP projects, land vesting in Government | 70% of affected families | Full Act; consent taken with the SIA |
Section 2(2)(b) | Acquisition for private companies for public purpose | 80% of affected families | Full Act; consent taken with the SIA |
Section 2(3) | Private purchase at or above prescribed limits | Not applicable | R&R obligations under Section 46 |
Public purpose is defined by enumeration (Section 2(1)): defence and national security; notified infrastructure excluding private hospitals, private educational institutions and private hotels; agro-processing, industrial corridors, mining; projects for project-affected families; housing; planned development and weaker-section housing; and homes for the calamity-displaced. The purpose must be stated in the notification and declaration, is tested in the SIA and the Section 8 examination, and remains reviewable, Singur being the standing warning. Consent is prior and informed, obtained along with the SIA through the 2014 Rules' Gram Sabha based, recorded procedure, counted per affected family (women separated by widowhood, divorce or desertion counting as families of their own); it supplements public purpose and cannot replace it, and a failed threshold simply ends the compulsory route. Section 105 keeps the thirteen Fourth Schedule statutes (National Highways Act, Railways Act and others) outside the Act, aligned since 1 January 2015 on its compensation and R&R standards, and Section 24 manages the 1894 transition.
8. The Definitions That Distribute the Act
- Affected family (Section 3(c)), six limbs: land losers; landless livelihood losers (agricultural labourers, tenants, sharecroppers, artisans, three years in the affected area); Forest Rights Act holders; Government assignees; forest and water dependents; and urban residents and livelihood losers. Compensation goes to those with interests in land; the R&R award goes to every affected family.
- Displaced family: the relocating subset, keyed to the housing, allowances and resettlement-infrastructure entitlements.
- Person interested: the hearing class, everyone claiming an interest in the compensation, including easement holders and State-law tenants.
- Land owner (Section 3(r)): the recorded owner, the Forest Rights Act grantee, the Government assignee, and the State-law owner, title beyond the revenue record.
- Marginal and small farmer: cultivation up to 1 hectare un-irrigated (0.5 irrigated) and up to 2 hectares un-irrigated (1 irrigated) respectively.
- The machinery: the appropriate Government (Central for Union, PSU and multi-State acquisitions; State otherwise) authorises; the Collector executes, survey, objections, both awards, possession, reference; the Requiring Body pays the whole cost of acquisition and performs its R&R obligations; the Administrator and Commissioner for R&R run rehabilitation, with a project-level R&R Committee at 100 acres.
- Land (Section 3(p)): includes benefits arising out of land and things attached to the earth, so buildings, trees and standing crops are valued with it.
9. The Part in Perspective
Three threads tie the foundations together. First, the Act is answer-shaped: each innovation, consent, SIA, the multiplier, statutory R&R, the narrowed urgency, Section 24, corresponds to a named failure of the 1894 regime. Second, the Act and the Constitution now move together: the Bimal Kumar Shah sub-rights read like the Act's own chapter headings, so even acquisitions outside the Act, under Fourth Schedule or State statutes, meet an Article 300A floor built to the same design. Third, the field is federal and contested: Entry 42 and Article 254(2) mean the Act the practitioner applies is the Act as amended in the State, and the consent and SIA provisions are precisely where the amendments bite.
⚠ Key point The 2013 Act (Act 30 of 2013, in force 1 January 2014) replaced the 1894 Act after Singur, Nandigram, Bhatta Parsaul and Ramji Veerji Patel. Constitutional frame: Entry 42 List III, Article 300A (K.T. Plantation; Vidya Devi; the seven Bimal Kumar Shah sub-rights), Articles 31A and 31B immunities, Article 254(2) State amendments. Identity: consent (80%/70%), SIA, food-security bar, multiplied compensation with 100% solatium, statutory R&R, Section 24, Section 101, the LARR Authority, 114 sections and four Schedules. Gateway: Section 2's three limbs; definitions: the six-limb affected family, displaced family, person interested, four-limb landowner, and the three-actor machinery of appropriate Government, Collector and Requiring Body. |
10. The Topics of This Part
- Topic 1: Introduction to the Act
- Topic 2: Evolution of land acquisition law, 1824 to 2013
- Topic 3: Defects of the 1894 Act and the case for reform
- Topic 4: Legislative history of the 2013 Act
- Topic 5: Preamble, objects and salient features
- Topic 6: Doctrine of eminent domain
- Topic 7: Right to property and Article 300A
- Topic 8: The constitutional framework
- Topic 9: Application of the Act: Section 2
- Topic 10: Key definitions under Section 3
- Topic 11: Public purpose under Section 2(1)
- Topic 12: The consent requirement
- Topic 13: Affected family, displaced family, person interested
- Topic 14: Appropriate Government, Collector and Requiring Body
- Topic 15: Land owner, small and marginal farmers, the landless